Work Profile Report [6W695]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : ‘शा.सं. 5663/।।।(2)/21- 46(एम0एल0ए0)/2017 टी0सी0 दिनांक 17.11.2021
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
97.80
Resanction Cost :
97.80
Tentative Cost :
97.80
Exp. Upto Last Fy :
0.01
For CFY 2024-2025
Remaining :
97.79
Demand :
1.59
Allotment :
2.61
Exp in CFY :
2.61
Total Up to Date Exp :
2.62
Alignment Approved
Sanction on : 3 years 1 month ago
17 Nov 2021
Physical Progress:
At start of FY 2024-2025 :
26 %
Up to Date :
26 %
Tentative Completion date on : 11 months 5 days from now
30 Nov 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
अधीक्षण अभिंयता के पत्र सं0 3097/465सी0-01/2024-25 दिनांक 09.07.2024 द्वारा पुनरीक्षित समरेखण प्रस्ताव अनुमोदित। -- as on 11-Jul-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: Pulbazar Bridge
© PWD Uttarakhand