Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 8 | 8 | 0.000 | 8 | 0.000 | 0.000 |
No of Bridges | 1 | 1 | 0 | 1 | 0 | 0 |
Span of Bridges [m] | 36 | 36 | 0.000 | 36 | 0.000 | 0.000 |
6W724 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई फाइत संख्या 36100 दिनांक 11.10.2022
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
21.36
Resanction Cost :
21.36
Tentative Cost :
21.36
Exp. Upto Last Fy : 0.07
For CFY 2024-2025
Remaining : 21.29
Demand : 0.50
Allotment : 0.00
Exp in CFY : 1.93
Total Up to Date Exp : 2.00
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 26 %
Up to Date : 26 %
Sanction on :
1 year 9 months ago
11 Oct 2022
Tentative Completion date:
1 year 1 week from now
31 Jul 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 01: Withdraw
Bottelneck: no issue
समरेखण प्रस्ताव पत्र सं0 2419/470 सी0-01/2024-25 दिनांक 24.05.2024 द्वारा अनुमोदित। -- as on 24-May-2024
Physical Peramenters