Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 2.000 | 3 | 3.000 | 2.000 |
6W741 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई फाइत संख्या 51057 दिनांक 31.03.2023
TS Amount (lakhs) : 280.28 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
281.50
Resanction Cost :
281.50
Tentative Cost :
281.50
Exp. Upto Last Fy : 73.31
For CFY 2024-2025
Remaining : 208.19
Demand : 96.00
Allotment : 92.10
Exp in CFY : 58.90
Total Up to Date Exp : 132.21
Construction Started
Physical Progress:
At start of FY 2024-2025 : 50 %
Up to Date : 85 %
Sanction on :
1 year 3 months ago
31 Mar 2023
Tentative Completion date:
2 months 4 weeks from now
15 Oct 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
4.00 किमी0 पार्ट ।। का कार्य पूर्ण।
पैरापिट निर्माण का कार्य प्रगति पर।
उक्त कार्य की निविदा 25 प्रतिशत कम दरों पर प्राप्त हुई है।
-- as on 05-Jul-2024
Physical Peramenters