Work Profile Report [6W741]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : ई फाइत संख्या 51057 दिनांक 31.03.2023
TS Amount (lakhs) : 280.28 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
281.50
Resanction Cost :
281.50
Tentative Cost :
200.00
Saving
81.50
Exp. Upto Last Fy :
73.31
For CFY 2024-2025
Remaining :
208.19
Demand :
118.90
Allotment :
92.10
Exp in CFY :
69.01
Total Up to Date Exp :
142.33
Construction Started
Sanction on : 1 year 7 months ago
31 Mar 2023
Physical Progress:
At start of FY 2024-2025 :
50 %
Up to Date :
85 %
Tentative Completion date on : 1 day 7 hours from now
25 Nov 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
पैरापिटों का निर्माण कार्य प्रगति पर है। -- as on 23-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: