Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 3.000 | 1 | 1.000 | 0.000 |
6W742 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई फाइत संख्या 51057 दिनांक 31.03.2023
TS Amount (lakhs) : 237.7 Lacs
Financial Detail
Sanction Cost : 237.70 Lacs
Resanction Cost : 237.70 Lacs
Exp. Upto Last Fy : 214.12 Lacs
For CFY 2024-2025
Remaining : 23.58 Lacs
Demand : 20.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.27 Lacs
Total Up to Date Exp : 214.39 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 80 %
Sanction on :
1 year 1 month ago
31 Mar 2023
Tentative Completion date:
3 months 1 week from now
31 Aug 2024
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 13: AIP DFO
Bottelneck: no issue
3.00 किमी0 पार्ट ।। का कार्य पूर्ण। कार्य प्रगति पर। -- as on 06-Mar-2024
Physical Peramenters