Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 3.000 | 1 | 1.000 | 1.000 |
6W742 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई फाइत संख्या 51057 दिनांक 31.03.2023
TS Amount (lakhs) : 237.7 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
237.70
Resanction Cost :
237.70
Tentative Cost :
237.70
Exp. Upto Last Fy : 214.12
For CFY 2024-2025
Remaining : 23.58
Demand : 20.00
Allotment : 1.33
Exp in CFY : 14.34
Total Up to Date Exp : 228.46
In Maintenance After Completion
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 100 %
Sanction on :
1 year 3 months ago
31 Mar 2023
Tentative Completion date:
1 month 1 week from now
31 Aug 2024
Actual Completion Date:
1 month 2 weeks ago
01 Jun 2024
Remark
Forest Status 13: AIP DFO
Bottelneck: no issue
कार्य पूर्ण।
अंतिम भुगतान की कार्यवाही उपरान्त पी0सी0सी0 एवं पी0सी0आर0 गठित की जानी है।
-- as on 04-Jul-2024
Physical Peramenters