Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 0.000 | 4 | 0.000 | 0.000 |
6W852 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई फाइत संख्या 51057 दिनांक 07.11.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
6.00
Resanction Cost :
6.00
Tentative Cost :
6.00
Exp. Upto Last Fy : 0.15
For CFY 2024-2025
Remaining : 5.85
Demand : 1.00
Allotment : 0.88
Exp in CFY : 0.88
Total Up to Date Exp : 1.03
Survey work done
Physical Progress:
At start of FY 2024-2025 : 10 %
Up to Date : 10 %
Sanction on :
8 months 1 week ago
07 Nov 2023
Tentative Completion date:
1 year 1 week from now
31 Jul 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
भूवैज्ञानिक निरीक्षण दिनांक 05.03.2024 को पूर्ण। आख्या प्राप्त। समरेखण प्रस्ताव गठित किया जा रहा है। -- as on 13-Jul-2024
Physical Peramenters