Work Profile Report [6W863]
Tenders
Aggrements
Project Activities
alerts
Documents
Administrative Approval Detail : शासनादेश सं0-5347/।।।(2)/2023-01(प्रा0आ0)/2023 दिनांक 05.12.2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : सड़क सुरक्षा कार्य ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
658.22
Resanction Cost :
658.22
Tentative Cost :
658.22
Exp. Upto Last Fy :
217.76
For CFY 2024-2025
Remaining :
440.46
Demand :
410.00
Allotment :
339.01
Exp in CFY :
0.00
Total Up to Date Exp :
217.76
Construction Started
Sanction on : 1 year 2 weeks ago
05 Dec 2023
Physical Progress:
At start of FY 2024-2025 :
10 %
Up to Date :
90 %
Tentative Completion date on : 1 week 2 days ago
15 Dec 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
क्रश बैरियर एवं पैरापिटों का कार्य पूर्ण। डेलीनेटर का कार्य प्रगति पर। -- as on 23-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand