Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 0 | 0 | 0 | 0 |
6W863 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0-5347/।।।(2)/2023-01(प्रा0आ0)/2023 दिनांक 05.12.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
658.22
Resanction Cost :
658.22
Tentative Cost :
658.22
Exp. Upto Last Fy : 217.76
For CFY 2024-2025
Remaining : 440.46
Demand : 420.00
Allotment : 162.05
Exp in CFY : 0.00
Total Up to Date Exp : 217.76
Construction Started
Physical Progress:
At start of FY 2024-2025 : 10 %
Up to Date : 20 %
Sanction on :
7 months 1 week ago
05 Dec 2023
Tentative Completion date:
1 month 2 weeks from now
01 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
क्रश बैरियर का कार्य प्रगति पर। -- as on 21-Mar-2024
Physical Peramenters