Work Profile Report [6W869]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : ई फाइत संख्या 51057/46 दिनांक 30.01.2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
6.00
Resanction Cost :
6.00
Tentative Cost :
6.00
Exp. Upto Last Fy :
1.11
For CFY 2025-2026
Remaining :
4.89
Demand :
0.60
Allotment :
0.58
Exp in CFY :
0.58
Total Up to Date Exp :
1.69
Alignment Approved
Sanction on : 1 year 10 months ago
30 Jan 2024
Physical Progress:
At start of FY 2025-2026 :
26 %
Up to Date :
26 %
Tentative Completion date on : 8 months 2 weeks from now
31 Aug 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
पिंलरों का निर्माण पूर्ण। वृक्षों के गणना की कार्यवाही गतिमान है। -- as on 29-Nov-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: