Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 0.000 | 4 | 0.000 | 0.000 |
6W869 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई फाइत संख्या 51057/46 दिनांक 30.01.2024
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
6.00
Resanction Cost :
6.00
Tentative Cost :
6.00
Exp. Upto Last Fy : 0.12
For CFY 2024-2025
Remaining : 5.88
Demand : 1.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.12
Survey work done
Physical Progress:
At start of FY 2024-2025 : 5 %
Up to Date : 5 %
Sanction on :
5 months 2 weeks ago
30 Jan 2024
Tentative Completion date:
1 year 1 month from now
31 Aug 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
सर्वेक्षण कार्य पूर्ण। अग्रिम कार्यवाही की जा रही है। -- as on 12-Apr-2024
Physical Peramenters