Work Profile Report [6W897]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : ई फाइल सं0 36100/46 दिनांक 01.08.2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
96.98
Resanction Cost :
96.98
Tentative Cost :
96.98
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
96.98
Demand :
10.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.00
Construction Started
Sanction on : 3 months 3 weeks ago
01 Aug 2024
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
0 %
Tentative Completion date on : 11 months 2 weeks from now
10 Nov 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर। -- as on 20-Nov-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand