Administrative Approval Detail : ई फाइल सं0 31978/46 दिनांक 17.12.2024/ राबै.उत्त.क्षे.का.एसपीडी 117487 R-16 RIDF XXXI DATED 12/11/2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
180.93
Resanction Cost :
180.93
Tentative Cost :
151.50
Saving
29.43
Exp. Upto Last Fy :
20.75
For CFY 2025-2026
Remaining :
160.18
Demand :
129.00
Allotment :
119.76
Exp in CFY :
119.76
Total Up to Date Exp :
140.51
In Maintenance After Completion
Sanction on : 11 months 4 weeks ago
17 Dec 2024
Physical Progress:
At start of FY 2025-2026 :
10 %
Up to Date :
100 %
Tentative Completion date on : 1 month 5 days ago
10 Nov 2025
Actual Completion Date : 1 month 3 days ago
12 Nov 2025
Physical Linear Components
Remark
Overall Saving 29.43 has been recorded as expected cost of work reduced from 180.93 to 151.50 . -- as on 09-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: