Work Profile Report [6W992]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : ई फाइल सं0 68052/46 दिनांक 23.05.2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
414.52
Resanction Cost :
414.52
Tentative Cost :
340.00
Saving
74.52
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
414.52
Demand :
190.00
Allotment :
20.19
Exp in CFY :
20.19
Total Up to Date Exp :
20.19
Construction Started
Sanction on : 8 months 7 hours ago
23 May 2025
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
6 %
Tentative Completion date on : 9 months 1 week from now
02 Nov 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
दीवारों का निर्माण कार्य प्रगति पर है। -- as on 17-Jan-2026
Assets :
Work not linked with IM
Bridges on The Basis of AI: