Work Profile Report [6W998]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : ई फाइल सं0 68052/46 दिनांक 04.08.2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
171.30
Resanction Cost :
171.30
Tentative Cost :
98.00
Saving
73.30
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
171.30
Demand :
97.00
Allotment :
22.22
Exp in CFY :
22.22
Total Up to Date Exp :
22.22
Construction Started
Sanction on : 4 months 1 week ago
04 Aug 2025
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
60 %
Tentative Completion date on : 9 months 1 week from now
23 Sep 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
3 किमी0 पहाड़ कटान का कार्य पूर्ण। अवशेष कार्य प्रगति पर। -- as on 08-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© 2025 PWD Uttarakhand