Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 4.250 | 0.75 | 0.000 | 0.000 |
70W105 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 1419/।।।(2)21-40(एम0एल0ए0) 2017 टी0सी0-1 दिनांक 31.05.2021
TS Amount (lakhs) : 93.89 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
93.89
Resanction Cost :
93.89
Tentative Cost :
93.89
Exp. Upto Last Fy : 92.42
For CFY 2024-2025
Remaining : 1.47
Demand : 1.47
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 92.42
In Maintenance After Completion
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 100 %
Sanction on :
3 years 1 month ago
31 May 2021
Tentative Completion date:
2 weeks 3 days ago
30 Jun 2024
Actual Completion Date:
3 months 2 weeks ago
31 Mar 2024
Remark
Bottelneck: no issue
पहाड़ कटान का कार्य 4.00 किमी0 लम्बाई में पूर्ण। किमी0 05 में खड्ड साइड में ग्रामवासियों के मकान क्षतिग्रस्त होने की सम्भावना से कार्य ग्रामवासियों द्वारा बाधित किया गया है जिसके कारण आगे कार्य कराया जाना सम्भव नहीं हो पा रहा है। अतः मार्ग 4.00 किमी0 लम्बाई में पूर्ण कर उक्त कार्य की पी0सी0आर0 शीघ्र प्रेषित की जा रही है। मार्ग का अनुरक्षण कार्य का पुनरीक्षित आगणन गठित कर स्वीकृति हेतु प्रेषित किया जा रहा है। -- as on 04-Jul-2024
Physical Peramenters