Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 0.000 | 4 | 0.000 | 0.000 |
70W142 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 7235/111(2)/11-139(प्रा0आ0)/2011 दिनांक 24.12.2011
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
50.40
Resanction Cost :
50.40
Tentative Cost :
50.40
Exp. Upto Last Fy : 19.95
For CFY 2024-2025
Remaining : 30.45
Demand : 5.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 19.95
Construction Started
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 20 %
Sanction on :
12 years 6 months ago
24 Dec 2011
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 13: AIP DFO
Bottelneck: no issue
उपरोक्त मोटर मार्ग की सैद्धान्तिक स्वीकृति प्राप्त होने के उपरान्त विधिवत स्वीकृति हेतु अनुपालन आख्या इस कार्यालय के पत्रांक सं0 2756/21सी0, दि0 27.08.2022 द्वारा प्रभागीय वनाधिकारी गढ़वाल वन प्रभाग पौड़ी को आॅफलाइन प्रेषित। भुगतान की गयी एन0पी0वी0 की धनराशि परिवेश पोर्टल पर आॅनलाइन न दिखने के कारण अनुपालन आख्या आॅनलाइन नहीं की जा सकी है। इस सम्बन्ध में परिवेश पोर्टल पर दि0 23.05.2024 के द्वारा शिकायत सं0 पी0ए0आर0-टी0आई0सी 24009279 एंव 24009297 के द्वारा आॅनलाइन शिकायत दर्ज करायी गयी है। -- as on 27-May-2024
Physical Peramenters