Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 0.000 | 2 | 0.000 | 0.000 |
70W19 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 4842(1)/।।।(2)/।।-30 (एम0एल0ए0)/2011
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 25.20 Lacs
Resanction Cost : 25.20 Lacs
Exp. Upto Last Fy : 11.65 Lacs
For CFY 2024-2025
Remaining : 13.55 Lacs
Demand : 3.55 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 11.65 Lacs
Technical sanction done
Physical Progress:
At start of FY 2024-2025 : 45 %
Up to Date : 45 %
Sanction on :
12 years 7 months ago
01 Oct 2011
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 13: AIP DFO
Bottelneck: no issue
उपरोक्त मोटर मार्ग की सैद्धान्तिक स्वीकृति प्राप्त होने के उपरान्त विधिवत स्वीकृति हेतु हेतु अनुपालन आख्या इस कार्यालय के पत्रांक सं0 1600/21सी0, दि0 30-05-2022 द्वारा प्रभागीय वनाधिकारी गढ़वाल वन प्रभाग पौड़ी को प्रेषित। -- as on 01-May-2024
Physical Peramenters