Work Profile Report [70W21]

कोटणीसैण के समीप ग्राम पैयागढ़ी -रजबौ मल्ला -दियोड मो0मार्ग का निर्माण
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शा0सं0 2755 /111-2/ 06(प्रा0आ0) /06 दिनांक 10.11.06

TS Amount (lakhs) : 250.75 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

258.75

Resanction Cost :

258.75

Tentative Cost :

258.75

Exp. Upto Last Fy :

248.82

For CFY 2024-2025

Remaining :

9.93

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

248.82

Construction Started

Sanction on : 18 years 3 months ago

11 Oct 2006

Physical Progress:

At start of FY 2024-2025 :

45 %

Up to Date :

45 %

Tentative Completion date on : 2 months 2 weeks from now

31 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
15
15
5.000
10
0.000
0.000

Remark

view all

भारत सरकार के कार्यालय द्वारा अधिरोपित आपत्तियों का निराकारण कर इस कार्यालय के पत्रांक 1627/21 सी0 दि 12.07.2024 के द्वारा डी0एफ0ओ0 गढ़वाल वन प्रभाग पौड़ी को प्रेषित। डी0एफ0ओ0 गढ़वाल वन प्रभाग पौड़ी के पत्रांक 2060/12 - 1 दिनाँक 12 -12-2024 के द्वारा रुपये 469530 एन0 पी0 वी0 की अतिरिक्त धनराशि की मांग की गयी है, जिस हेतु इस कार्यालय का पत्रांक 2940 /21 सी दिनाँक 13-12-2024 के द्वारा अधीक्षण अभियंता महोदय से धनावंटन की मांग की गयी है। -- as on 07-Jan-2025

Rating : 98

Forest Case Pending At : 11: AIP Division

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Roads on The Basis of AI: Road 1

Bridges on The Basis of AI: