Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 10 | 10 | 0.000 | 10 | 0.000 | 0.000 |
70W222 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 5341/।।।(2)/18-36(एम0एल0ए0)/ 201 /टी0सी0 दि0 02.11.2018
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 79.60 Lacs
Resanction Cost : 79.60 Lacs
Exp. Upto Last Fy : 6.26 Lacs
For CFY 2024-2025
Remaining : 73.34 Lacs
Demand : 2.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 6.26 Lacs
Unstarted Work
Physical Progress:
At start of FY 2024-2025 : 30 %
Up to Date : 30 %
Sanction on :
5 years 6 months ago
02 Nov 2018
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
5.00 K.M. में द्वितीय चरण स्टेज-1 की स्वीकृति प्राप्त। मुआवजा गठन की कार्यवाही प्रगति पर। -- as on 28-Mar-2024
Physical Peramenters