Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 0.000 | 4 | 0.000 | 0.000 |
70W317 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 429(1)/111(2)/22-40(एम0एल0ए0)2017 दिनांक 06.01.2022
TS Amount (lakhs) : 3.8 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
38.40
Resanction Cost :
38.40
Tentative Cost :
38.40
Exp. Upto Last Fy : 5.30
For CFY 2024-2025
Remaining : 33.10
Demand : 2.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 5.30
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 15 %
Up to Date : 15 %
Sanction on :
2 years 6 months ago
06 Jan 2022
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
सर्वेक्षण का कार्य पूर्ण। मुआवजा गठन की कार्यवाही प्रगति पर। संरेखण स्वीकृत। डी0पी0आर0 गठन की कार्यवाही प्रगति पर। -- as on 02-Jun-2024
Physical Peramenters