Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 0.000 | 5 | 5.000 | 5.000 |
70W400 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई0 फाईल न0 36089 दि0 31-03-2023
TS Amount (lakhs) : 343.61 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
343.61
Resanction Cost :
343.61
Tentative Cost :
343.61
Exp. Upto Last Fy : 310.21
For CFY 2024-2025
Remaining : 33.40
Demand : 20.00
Allotment : 0.00
Exp in CFY : 8.57
Total Up to Date Exp : 318.78
Work completed
Physical Progress:
At start of FY 2024-2025 : 50 %
Up to Date : 100 %
Sanction on :
1 year 3 months ago
31 Mar 2023
Tentative Completion date:
3 months 2 weeks from now
02 Nov 2024
Actual Completion Date:
3 weeks 4 days ago
22 Jun 2024
Remark
Bottelneck: no issue
दायित्वों का अन्तिमीकरण कर पी0सी0आर0 शीघ्र प्रेषित की जा रही है। -- as on 22-May-2024
Physical Peramenters