Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 0.000 | 4 | 4.000 | 0.000 |
70W416 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासन की ई0 पत्रावली सं0 50713, दि0 15.03.2023
TS Amount (lakhs) : 286.77 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
286.77
Resanction Cost :
286.77
Tentative Cost :
286.77
Exp. Upto Last Fy : 53.77
For CFY 2024-2025
Remaining : 233.00
Demand : 194.17
Allotment : 100.00
Exp in CFY : 83.48
Total Up to Date Exp : 137.25
Construction Started
Physical Progress:
At start of FY 2024-2025 : 15 %
Up to Date : 60 %
Sanction on :
1 year 4 months ago
15 Mar 2023
Tentative Completion date:
5 months 2 weeks from now
04 Jan 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
इण्टर कोट का कार्य पूर्ण। टोप कोट का कार्य प्रगति पर। -- as on 22-May-2024
Physical Peramenters