Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 0.000 | 4 | 4.000 | 0.000 |
70W416 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासन की ई0 पत्रावली सं0 50713, दि0 15.03.2023
TS Amount (lakhs) : 286.77 Lacs
Financial Detail
Sanction Cost : 286.77 Lacs
Resanction Cost : 286.77 Lacs
Exp. Upto Last Fy : 53.77 Lacs
For CFY 2024-2025
Remaining : 233.00 Lacs
Demand : 100.00 Lacs
Allotment : 50.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 53.77 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 15 %
Up to Date : 15 %
Sanction on :
1 year 2 months ago
15 Mar 2023
Tentative Completion date:
6 months 1 week from now
30 Nov 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
सोलिंग का कार्य पूर्ण। दीवार निर्माण, इण्टर कोट का कार्य प्रगति पर। -- as on 01-Mar-2024
Physical Peramenters