Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
No of Bridges | 1 | 1 | 0 | 1 | 0 | 0 |
Span of Bridges [m] | 60 | 60 | 0.000 | 60 | 0.000 | 0.000 |
70W421 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0 की ई0 पत्रावली संख्या 49198, दिनांक-18.05.2023
TS Amount (lakhs) : 15.6 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
15.60
Resanction Cost :
15.60
Tentative Cost :
15.60
Exp. Upto Last Fy : 0.18
For CFY 2024-2025
Remaining : 15.42
Demand : 5.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.18
Survey work done
Physical Progress:
At start of FY 2024-2025 : 10 %
Up to Date : 10 %
Sanction on :
1 year 1 month ago
18 May 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
सर्वेक्षण कार्य पूर्ण। भू-वैज्ञानिक के निरीक्षण के उपरान्त रिपोर्ट प्राप्त। अधीक्षण अभियन्ता द्वारा स्थल चयन किया जा चुका है। रिपोर्ट प्राप्त की जा रही है। -- as on 20-Jun-2024
Physical Peramenters