Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
No of Bridges | 1 | 1 | 0 | 1 | 0 | 0 |
Span of Bridges [m] | 60 | 60 | 0.000 | 60 | 0.000 | 0.000 |
70W421 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0 की ई0 पत्रावली संख्या 49198, दिनांक-18.05.2023
TS Amount (lakhs) : 15.6 Lacs
Financial Detail
Sanction Cost : 15.60 Lacs
Resanction Cost : 15.60 Lacs
Exp. Upto Last Fy : 0.18 Lacs
For CFY 2024-2025
Remaining : 15.42 Lacs
Demand : 5.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.18 Lacs
Survey work done
Physical Progress:
At start of FY 2024-2025 : 10 %
Up to Date : 10 %
Sanction on :
1 year 1 day ago
18 May 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
सर्वेक्षण कार्य पूर्ण। भू-वैज्ञानिक के निरीक्षण के उपरान्त रिपोर्ट प्राप्त। अधीक्षण अभियन्ता द्वारा स्थल चयन किया जाना है। -- as on 07-Mar-2024
Physical Peramenters