Work Profile Report [70W422]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0 की ई0 पत्रावली संख्या 49198, दिनांक-18.05.2023
TS Amount (lakhs) : 12.48 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
12.48
Resanction Cost :
12.48
Tentative Cost :
12.48
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
12.48
Demand :
5.00
Allotment :
9.00
Exp in CFY :
2.90
Total Up to Date Exp :
2.90
Alignment Approved
Sanction on : 1 year 7 months ago
18 May 2023
Physical Progress:
At start of FY 2024-2025 :
10 %
Up to Date :
40 %
Tentative Completion date on : 6 days 34 minutes from now
31 Dec 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
पी0पी0आर0 डिजाइन सैल देहरादून द्वारा अनुमोदित कर दी गयी है। डी0पी0आर0 गठन की कार्यवाही प्रगति पर। -- as on 15-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: