Work Profile Report [70W47]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 3867(0)/।।।(2)/17-40/(एमएलए) /2017 दि0 06.12.2017
TS Amount (lakhs) : 5.69 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
16.75
Resanction Cost :
16.75
Tentative Cost :
16.75
Exp. Upto Last Fy :
2.67
For CFY 2024-2025
Remaining :
14.08
Demand :
4.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
2.67
Construction Started
Sanction on : 6 years 11 months ago
06 Dec 2017
Physical Progress:
At start of FY 2024-2025 :
35 %
Up to Date :
40 %
Tentative Completion date on : 4 months 1 week from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
द्वितीय चरण स्टेज-1 की स्वीकृति प्राप्त। मुआवजा भुगतान अवशेष है। -- as on 02-Sep-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: