Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.5 | 1.5 | 0.000 | 1.5 | 0.000 | 0.000 |
70W474 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासन की ई0 पत्रावली सं0-38629, दिनांक 18.10.2023
TS Amount (lakhs) : 2.25 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
2.25
Resanction Cost :
2.25
Tentative Cost :
2.25
Exp. Upto Last Fy : 0.36
For CFY 2024-2025
Remaining : 1.89
Demand : 1.50
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.36
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 60 %
Sanction on :
8 months 4 weeks ago
18 Oct 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
संरेखण स्वीकृत। डी0पी0आर0 गठित कर अधी0अभि0 पौड़ी को प्रेषित। -- as on 01-Jul-2024
Physical Peramenters