Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 0.000 | 2 | 0.000 | 0.000 |
70W476 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासन की ई0 पत्रावली सं0 50713, दि0 30.10.2023
TS Amount (lakhs) : 3 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
3.00
Resanction Cost :
3.00
Tentative Cost :
3.00
Exp. Upto Last Fy : 0.25
For CFY 2024-2025
Remaining : 2.75
Demand : 1.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.25
Survey work done
Physical Progress:
At start of FY 2024-2025 : 10 %
Up to Date : 10 %
Sanction on :
8 months 2 weeks ago
30 Oct 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
सर्वेक्षण का कार्य पूर्ण। संरेखण गठन की कार्यवाही प्रगति पर। -- as on 01-Mar-2024