Work Profile Report [70W49]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 3867(0)/।।।(2)/17-40/(एमएलए) /2017 दि0 06.12.2017
TS Amount (lakhs) : 2.56 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
8.37
Resanction Cost :
8.37
Tentative Cost :
8.37
Exp. Upto Last Fy :
0.96
For CFY 2024-2025
Remaining :
7.41
Demand :
1.41
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.96
Construction Started
Sanction on : 7 years 2 weeks ago
06 Dec 2017
Physical Progress:
At start of FY 2024-2025 :
15 %
Up to Date :
20 %
Tentative Completion date on : 2 months 3 days from now
28 Feb 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
प्रथम चरण के कार्य पूर्ण। मुआवजा अवशेष है। -- as on 03-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand