Work Profile Report [70W540]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासन की ई0 पत्रावली सं0 38666, दि0 19.07.2024
TS Amount (lakhs) : 688.04 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
344.02
Resanction Cost :
344.02
Tentative Cost :
344.02
Exp. Upto Last Fy :
302.27
For CFY 2025-2026
Remaining :
41.75
Demand :
30.36
Allotment :
30.35
Exp in CFY :
30.35
Total Up to Date Exp :
332.62
Work completed
Sanction on : 1 year 4 months ago
19 Jul 2024
Physical Progress:
At start of FY 2025-2026 :
75 %
Up to Date :
100 %
Tentative Completion date on : 5 months 1 week ago
15 Jun 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 30-Oct-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: