Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 4.000 | 0 | 0.000 | 0.000 |
70W6 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 1373/।।।(2)21-40(एम0एल0ए0) 2017 टी0सी0 4 दिनांक 21.05.2021
TS Amount (lakhs) : 80.76 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
80.76
Resanction Cost :
80.76
Tentative Cost :
80.76
Exp. Upto Last Fy : 80.31
For CFY 2024-2025
Remaining : 0.45
Demand : 0.45
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 80.31
In Maintenance After Completion
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
3 years 1 month ago
21 May 2021
Tentative Completion date:
11 months 2 weeks ago
31 Jul 2023
Actual Completion Date:
1 year 6 months ago
31 Dec 2022
Remark
Bottelneck: no issue
कार्य पूर्ण। कार्य की पी0सी0आर0 आपत्तियों के निराकरण के उपरान्त अधीक्षण अभियन्ता पौड़ी के पत्रांक 478/783 याता0-12/2023, दि0 29.02.2024 द्वारा मुख्य अभियन्ता पौड़ी को प्रेषित। -- as on 06-Mar-2024
Physical Peramenters