Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 8 | 7.2 | 7.250 | -0.05 | 0.000 | 0.000 |
70W85 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 337/।।।(2)/09-43(प्रा0आ0)/09 दि0 12.03.2010
TS Amount (lakhs) : 360.04 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
280.00
Resanction Cost :
360.04
Tentative Cost :
360.04
Exp. Upto Last Fy : 331.06
For CFY 2024-2025
Remaining : 28.98
Demand : 15.14
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 331.06
In Maintenance After Completion
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
14 years 4 months ago
13 Mar 2010
Tentative Completion date:
9 months 2 weeks ago
28 Sep 2023
Actual Completion Date:
3 months 2 weeks ago
28 Mar 2024
Remark
Bottelneck: no issue
नाबार्ड के अन्तर्गत स्वीकृत लम्बाई 4.50 किमी लागत 280.00 लाख में कार्य पूर्ण। कार्य की पी0सी0आर0 अधीक्षण अभियन्ता पौड़ी के पत्रांक 623/783 याता0-12/2023, दि0 23.02.2024 द्वारा मुख्य अभियन्ता पौड़ी को प्रेषित।। कार्य की राज्य योजना के अन्तर्गत 360.04 लाख (280.00+80.04 लाख) की पुनरीक्षित स्वीकृति 4.50+2.70 =7.20 किमी0 पहाड़ कटान हेतु प्राप्त हुयी है जिसका कार्य राज्य योजना गया है।
राज्य योजना के अन्तर्गत पुनरीक्षित स्वीकृत लम्बाई 2.70 किमी0 में पहाड़ कटान के सापेक्ष 2.70 किमी0 लम्बाई मे पहाड़ कटान का कार्य पूर्ण ।दायित्वों का अन्तिमीकरण किया जा रहा है।
-- as on 28-Mar-2024
Physical Peramenters