Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 0.000 | 3 | 0.000 | 0.000 |
70W88 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 6467/111(2)11-12(प्रा0आ0)/11 दि0 22.12.2011
TS Amount (lakhs) : 22.43 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
37.74
Resanction Cost :
37.74
Tentative Cost :
37.74
Exp. Upto Last Fy : 10.82
For CFY 2024-2025
Remaining : 26.92
Demand : 6.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 10.82
Construction Started
Physical Progress:
At start of FY 2024-2025 : 45 %
Up to Date : 45 %
Sanction on :
12 years 6 months ago
22 Dec 2011
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
द्वितीय चरण की स्वीकृति प्राप्त। मुआवजा भुगतान अवशेष। -- as on 28-Mar-2024
Physical Peramenters