Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 0.000 | 3 | 2.000 | 0.000 |
71W1016 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई पत्रावली संख्या 38629 दिनांक 14/03/2024
TS Amount (lakhs) : 178 Lacs
Financial Detail
Sanction Cost : 178.00 Lacs
Resanction Cost : 178.00 Lacs
Exp. Upto Last Fy : 16.91 Lacs
For CFY 2024-2025
Remaining : 161.09 Lacs
Demand : 142.50 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 16.91 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
2 months 5 days ago
14 Mar 2024
Tentative Completion date:
9 months 1 week from now
28 Feb 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 06-Apr-2024
Physical Peramenters