Administrative Approval Detail : शा0सं0-868-।।।-3-2025/सी0आर0आई0एफ0/ई-69924 दिनांक 18/7/2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : CRIF ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
2309.47
Resanction Cost :
2309.47
Tentative Cost :
2309.47
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
2,309.47
Demand :
1,000.00
Allotment :
923.79
Exp in CFY :
0.00
Total Up to Date Exp :
0.00
in Tendering Stage
Sanction on : 3 weeks 9 hours ago
18 Jul 2025
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
0 %
Tentative Completion date on : 1 year 7 months from now
31 Mar 2027
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
टैक्निकल बिड खोल दी गई है। ई0 वैल्यूवेशन का कार्य प्रगति पर । -- as on 02-Aug-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: