Work Profile Report [71W1125]
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : ई0 पत्रावली सं0-33334 दिनांक 4/8/2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
85.49
Resanction Cost :
85.49
Tentative Cost :
85.49
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
85.49
Demand :
15.00
Allotment :
0.33
Exp in CFY :
0.33
Total Up to Date Exp :
0.33
Construction Started
Sanction on : 4 months 1 week ago
04 Aug 2025
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
0 %
Tentative Completion date on : 3 months 2 weeks from now
31 Mar 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Excess requirement 85.49 has been counted as tentative cost increased from to 85.49 .
अनुबन्ध गठन की कार्यवाही की जा रही है।
-- as on 11-Nov-2025