Work Profile Report [71W1126]
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : ई0 पत्रावली सं0-69420 दिनांक 4/8/2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
951.88
Resanction Cost :
951.88
Tentative Cost :
951.88
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
951.88
Demand :
100.57
Allotment :
105.16
Exp in CFY :
105.83
Total Up to Date Exp :
105.83
Construction Started
Sanction on : 5 months 2 weeks ago
04 Aug 2025
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
0 %
Tentative Completion date on : 1 year 2 months from now
31 Mar 2027
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Excess requirement 951.88 has been counted as tentative cost increased from to 951.88 .
कार्य प्रगति पर।
-- as on 07-Jan-2026
Assets :
Work not linked with IM
Bridges on The Basis of AI: