Administrative Approval Detail : शा0सं0-6467/।।।(2)/11-121 (प्रा0आ0)/11 दि0 22/12/11
TS Amount (lakhs) : 176.06 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
176.40
Resanction Cost :
176.40
Tentative Cost :
176.40
Exp. Upto Last Fy :
19.52
For CFY 2025-2026
Remaining :
156.88
Demand :
2.00
Allotment :
2.00
Exp in CFY :
2.02
Total Up to Date Exp :
21.54
Construction Started
Sanction on : 13 years 7 months ago
22 Dec 2011
Physical Progress:
At start of FY 2025-2026 :
11 %
Up to Date :
15 %
Tentative Completion date on : 2 months 6 days from now
15 Oct 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
fद्वतीय चरण की स्वीकृfत प्राप्त। -- as on 14-Jun-2021