Work Profile Report [71W586]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0-605/।।।(2)/19-36(एम0एल0ए0)/2017 दि0 7/2/2019
TS Amount (lakhs) : 52.7 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
52.70
Resanction Cost :
52.70
Tentative Cost :
52.70
Exp. Upto Last Fy :
1.28
For CFY 2025-2026
Remaining :
51.42
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
1.28
Construction Started
Sanction on : 6 years 10 months ago
07 Feb 2019
Physical Progress:
At start of FY 2025-2026 :
2 %
Up to Date :
2 %
Tentative Completion date on : 2 years 11 months from now
20 Dec 2028
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
fद्वतीय चरण की स्वीकृfत प्राप्त। -- as on 14-Jun-2021
Assets :
Work not linked with IM
Bridges on The Basis of AI: