Work Profile Report [71W716]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0-3260/।।। (2)/ 21- 41 (एम0एल0ए0) /2017 दिनांक 2/9/2021
TS Amount (lakhs) : 285.11 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
285.11
Resanction Cost :
285.11
Tentative Cost :
170.86
Saving
114.25
Exp. Upto Last Fy :
170.86
For CFY 2024-2025
Remaining :
114.25
Demand :
1.23
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
170.86
In Maintenance After Completion
Sanction on : 3 years 3 months ago
02 Sep 2021
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 9 months 3 weeks ago
29 Feb 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Saving 114.25 has been recorded as expected cost of work reduced from 285.11 to 170.86 .
कार्य की पी0सी0आर0/पी0सी0सी0 मुख्य अभियन्ता पौड़ी के पत्रांक-1787/73 नाबार्ड (पी0सी0आर0)-पौड़ी/2023 दि0 10/5/2023 द्वारा प्रमुख अभियन्ता, उत्तराखण्ड लो0नि0वि0, देहरादून को प्रेषित।
-- as on 03-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: