Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 3 | 0 |
71W864 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 38666/111503 दिनांक 31/3/2023
TS Amount (lakhs) : 4.5 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
4.50
Resanction Cost :
4.50
Tentative Cost :
4.50
Exp. Upto Last Fy : 0.10
For CFY 2024-2025
Remaining : 4.40
Demand : 1.50
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.10
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
1 year 3 months ago
31 Mar 2023
Tentative Completion date:
3 months 3 weeks ago
20 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
संरेखण प्रस्ताव अधीक्षण अभियन्ता, पौड़ी के पत्रांक-8129/1567 याता-12/23 दिनांक 18/11/2023 द्वारा स्वीकृत। इस कार्यालय के पत्रांक-563/2सी0 दिनांक 7/2/24 द्वारा रू0 102.50 लाख मात्र का विस्तृत आगणन अधीक्षण अभियन्ता, पौड़ी को प्रेषित। मुख्य अभियन्ता पौड़ी के पत्रांक-918/12 (116) याता-दुगड्डा (पौड़ी)/2022 दिनांक 12/3/2024 द्वारा रू0 102.50 लाख मात्र का सचिव, लो0नि0वि0, उत्तराखण्ड शासन को प्रेषित। -- as on 27-Jun-2024
Physical Peramenters