Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 0.000 | 5 | 3.000 | 1.500 |
71W961 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई पत्रावली संख्या 33725 दिनांक 27/10/2023
TS Amount (lakhs) : 149.59 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
149.59
Resanction Cost :
149.59
Tentative Cost :
149.59
Exp. Upto Last Fy : 0.26
For CFY 2024-2025
Remaining : 149.33
Demand : 100.00
Allotment : 38.05
Exp in CFY : 34.09
Total Up to Date Exp : 34.35
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 35 %
Sanction on :
8 months 2 weeks ago
27 Oct 2023
Tentative Completion date:
8 months 1 week from now
26 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 05-Apr-2024
Physical Peramenters