Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 10 | 7.13 | 7.13 | 0 |
72W153 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 2855/।।।(2)/11-39 (प्रा0आ0)/2011 दि0 06.07.2011
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 126.00 Lacs
Resanction Cost : 126.00 Lacs
Exp. Upto Last Fy : 42.77 Lacs
For CFY 2024-2025
Remaining : 83.23 Lacs
Demand : 45.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 42.77 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 76 %
Up to Date : 76 %
Sanction on :
12 years 10 months ago
06 Jul 2011
Tentative Completion date:
10 months 1 week from now
30 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 13: AIP DFO
Bottelneck: no issue
8बी/यू0सी0पी0/06/130/2016/एफ0सी0/1131 दि0 19.10.2016 द्वारा सैद्धान्तिक स्वीकृति प्राप्त। मोटर मार्ग के समरेखणान्तर्गत पडने वाले बाधक पेडो का छपान एवं पातन किया जा चुका हे। सैद्धान्तिक स्वीकृति में दी गई शर्तो का विन्दृबार निराकरण कर इस कार्यालय के पत्रांक 1842/14सी दि0 09.12.2019 द्वारा प्रभागीय वनाधिकारी गढ़वाल वनप्रभाग पौडी को पत्र लिखा गया है। विधिवत स्वीकृति प्राप्त किये जाने हेतु इस कार्यालय के पत्रांक 512/14सी0 दि0 30.03.2021 के द्वारा अपर प्रमुख वन संरक्षक भारत सरकार, पर्यायवरण, वन एवं जलवायु परिवर्तन मंत्रालय, क्षेत्रीय कार्यालय (उत्तर-मध्य क्षेत्र), सुभाषरोड देहरादून को पत्र लिखा गया है। पुनः पत्रांक 868/14सी0 दि0 05.07.21 के द्वारा अनुस्मारक पत्र लिखा गया है। मुआवजा शेष। द्वितीय चरण की स्वीकृति प्राप्त एवं द्वितीय चरण का कार्य पूर्ण। -- as on 05-Nov-2023
Physical Peramenters