Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 3 | 0 | ||
No of Bridges | 1 | 1 | 1 | 0 | ||
Span of Bridges [m] | 40 | 48 | 48 | 0 |
72W159 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 4996)/।।।(2)/।।-84(प्रा0आ0)/2011 दि0 23.11.2011
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
40.48
Resanction Cost :
40.48
Tentative Cost :
40.48
Exp. Upto Last Fy : 11.16
For CFY 2024-2025
Remaining : 29.32
Demand : 5.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 11.16
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 26 %
Up to Date : 26 %
Sanction on :
12 years 7 months ago
23 Nov 2011
Tentative Completion date:
1 year 8 months from now
30 Mar 2026
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
समरेखण एवं सेतु का स्थल चयन पूर्ण। मार्ग की डी0पी0आर0 अधीक्षण अभियन्ता, 12वाॅ वृत्त, लो0नि0वि0 पौडी के पत्रांक 1969/1244 याता0-12/2023 दि0 26.05.2023 द्वारा मुख्य अभियन्ता, लो0नि0वि0 पौडी को प्रेषित। मुख्य अभियन्ता स्तर से आपत्तियो में प्राप्त। आपत्तियो का निराकरण किया जा रहा है। -- as on 05-Sep-2023
Physical Peramenters