Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 5 | 0 |
72W224 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 815/111(2)/ 14 -57 (प्रा0आ0)/13 दिनाॅक 8/2/2014
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
37.20
Resanction Cost :
37.20
Tentative Cost :
37.20
Exp. Upto Last Fy : 11.21
For CFY 2024-2025
Remaining : 25.99
Demand : 2.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 11.21
Construction Started
Physical Progress:
At start of FY 2024-2025 : 76 %
Up to Date : 76 %
Sanction on :
10 years 5 months ago
08 Feb 2014
Tentative Completion date:
8 months 1 week from now
30 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
प्रथम चरण का कार्य पूर्ण। मुआवजा शेष। द्वितीय चरण की स्वीकृति प्राप्त। -- as on 31-Jul-2020
Physical Peramenters