Work Profile Report [72W224]
Remarks
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 815/111(2)/ 14 -57 (प्रा0आ0)/13 दिनाॅक 8/2/2014
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
37.20
Resanction Cost :
37.20
Tentative Cost :
37.20
Exp. Upto Last Fy :
11.21
For CFY 2024-2025
Remaining :
25.99
Demand :
2.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
11.21
Construction Started
Sanction on : 10 years 9 months ago
08 Feb 2014
Physical Progress:
At start of FY 2024-2025 :
76 %
Up to Date :
76 %
Tentative Completion date on : 4 months 6 days from now
30 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
प्रथम चरण का कार्य पूर्ण। मुआवजा शेष। द्वितीय चरण की स्वीकृति प्राप्त। -- as on 31-Jul-2020
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand