Work Profile Report [72W241]
Remarks
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 1903/।।।(2)/15-05(प्रा0आ0)/2015 दि0 20.03.2015
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
15.36
Resanction Cost :
15.36
Tentative Cost :
15.36
Exp. Upto Last Fy :
8.31
For CFY 2024-2025
Remaining :
7.05
Demand :
2.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
8.31
Construction Started
Sanction on : 9 years 9 months ago
20 Mar 2015
Physical Progress:
At start of FY 2024-2025 :
76 %
Up to Date :
76 %
Tentative Completion date on : 3 months 5 days from now
30 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
प्रथम चरण का कार्य पूर्ण। मुआवजा शेष। द्वितीय चरण की स्वीकृति प्राप्त। -- as on 31-Jul-2020
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand