Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 3 | 0 |
72W241 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 1903/।।।(2)/15-05(प्रा0आ0)/2015 दि0 20.03.2015
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
15.36
Resanction Cost :
15.36
Tentative Cost :
15.36
Exp. Upto Last Fy : 8.31
For CFY 2024-2025
Remaining : 7.05
Demand : 2.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 8.31
Construction Started
Physical Progress:
At start of FY 2024-2025 : 76 %
Up to Date : 76 %
Sanction on :
9 years 3 months ago
20 Mar 2015
Tentative Completion date:
8 months 1 week from now
30 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
प्रथम चरण का कार्य पूर्ण। मुआवजा शेष। द्वितीय चरण की स्वीकृति प्राप्त। -- as on 31-Jul-2020
Physical Peramenters