Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 6 | 6 | 6 | 0 | ||
No of Bridges | 1 | 1 | 1 | 0 | ||
Span of Bridges [m] | 40 | 40 | 40 | 0 |
72W246 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : मा0 मुख्यमंत्री जी की घोषणान्तर्गत अपर सचिव महोदय उत्तराखण्ड शासन के शा0सं0 2997/।।।(2)15-06(मा0मु0घो0)/2015 दि0 08.05.2015 के द्वारा स्वीकृति प्राप्त।
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 47.32 Lacs
Resanction Cost : 47.32 Lacs
Exp. Upto Last Fy : 8.30 Lacs
For CFY 2024-2025
Remaining : 39.02 Lacs
Demand : 5.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 8.30 Lacs
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 20 %
Up to Date : 20 %
Sanction on :
9 years 1 week ago
08 May 2015
Tentative Completion date:
1 year 10 months from now
30 Mar 2026
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 02: Division
Bottelneck: no issue
संशोधित समरेखण पर अनुमोदन प्राप्त। क्षतिपूरक वृक्षारोपण भूमि उपलब्ध कराने हेतु इस कार्यालय के पत्रांक 1446/14सी0 दि0 14.11.2022 एवं पत्रांक 404/14सी0 दि0 18.03.2023 द्वारा जिलाधिकारी, गढवाल को पत्र लिखा गया है।जिलाधिकारी महोदय पौडी द्वारा आवंटित क्षतिपूरक वृक्षारोपण हेतु भूमि का सुयक्त निरीक्षण किये जाने हेतु दि0 12.09.2023 की तिथि निर्धारित की गयी है। डिजीटल मैप बनाये जाने हेतु कार्यवाही गतिमान है। मार्ग में पडने वाले सेतु का डिजाइन एवं डी0पी0आर0 प्राप्त हो चुकी है। -- as on 30-Dec-2023
Physical Peramenters