Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 10 | 7.15 | 7.15 | 0 |
72W248 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : मा0 मुख्यमंत्री जी की घोषणान्तर्गत अपर सचिव महोदय उत्तराखण्ड शासन के शा0सं0 4520/।।।(2)15-08(मा0मु0घो0)/2015 दि0 19.06.2015 के द्वारा स्वीकृति प्राप्त।
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 25.70 Lacs
Resanction Cost : 25.70 Lacs
Exp. Upto Last Fy : 1.15 Lacs
For CFY 2024-2025
Remaining : 24.55 Lacs
Demand : 5.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 1.15 Lacs
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 20 %
Up to Date : 20 %
Sanction on :
8 years 11 months ago
19 Jun 2015
Tentative Completion date:
1 year 10 months from now
30 Mar 2026
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 03: DM
Bottelneck: no issue
जिलाधिकारी पौडी गढवाल के पत्र सं0 1037/08-भूमि0 अध्य0 लि0-भूमि0हस्ता0/2021 र्पाडी दि0 05.08.2021 के द्वारा क्षतिपूरक वृक्षारोपण हतु दोगुनी सिविल भुमि नाॅन0जेड0ए0 श्रेणी 9 (2)झाडी खाता सं0-07 के खसरा सं0 1078 रकवा 4.213 है0 सिविल भुमि वन विभाग, पौडी के नाम हस्तारण की स्वीकृति प्रदान की गई हें। उक्त भूमि का संयुक्त निरीक्षण दि0 17.05.2022 को किया गया। निरीक्षण में उक्त भूमि को अनुपयुक्त पाया गया। पुनः क्षतिपूरक भूमि उपलब्ध कराने हेत इस कार्यालय के पत्रांक 902/14सी0 दि0 13.07.2022, पत्रांक 404/14सी0 दि0 18.03.2023 एवं पत्रांक 1253/14सी0 दि0 02.08.2023 द्वारा जिलाधिकारी महोदय को द्वितीय अनुस्मारक पत्र लिखा गया है। -- as on 30-Dec-2023
Physical Peramenters