Work Profile Report [72W27]

जोगीमढी-सराईखेत (कटपतिया होते हुये) मोटर मार्ग।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : 2228/111-2-06-32 (प्रा0आ0)/06 टी0सी0 दि0 2-9-06

TS Amount (lakhs) : 199.28 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

225.25

Resanction Cost :

225.25

Tentative Cost :

225.25

Exp. Upto Last Fy :

225.21

For CFY 2025-2026

Remaining :

0.04

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

225.21

Work completed

Sanction on : 18 years 9 months ago

02 Sep 2006

Physical Progress:

At start of FY 2025-2026 :

100 %

Up to Date :

100 %

Tentative Completion date on : 11 months 4 days ago

30 Jun 2024

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
13
6.25
6.25
-

Remark

view all

सोलिंग का कार्य पूण। अन्य अवशेष कार्य प्रगति पर। -- as on 30-Mar-2024

Rating : 100

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI:

© PWD Uttarakhand