Work Profile Report [72W270]

मैखुली-देवराडी-कठूरखाल-गणतखाल मोटर मार्ग के कि0मी0 23 से 25 का निर्माण कार्य।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : 1809/।।।(2)/16-38(एम0एल0ए0)/2015 टी0सी0 दि0 26.05.2016

TS Amount (lakhs) : 160 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

160.00

Resanction Cost :

160.00

Tentative Cost :

160.00

Exp. Upto Last Fy :

144.43

For CFY 2025-2026

Remaining :

15.57

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

144.43

Work completed

Sanction on : 9 years 1 week ago

26 May 2016

Physical Progress:

At start of FY 2025-2026 :

90 %

Up to Date :

90 %

Tentative Completion date on : 2 months 4 days ago

30 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
3
3
0.000
3
0.000
0.000

Remark

view all

कार्य पूर्ण। मुआवजे का वितरण किया जाना शेष है। अमीनो की कमी के कारण कार्य बाधित। -- as on 07-Nov-2023

Rating : 90

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: