Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 5 | 0 |
72W293 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 06/।।।(2)/17-23(प्रा0आ0)/2016 दि0 04 जनवरी 2017
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
16.85
Resanction Cost :
16.85
Tentative Cost :
16.85
Exp. Upto Last Fy : 0.20
For CFY 2024-2025
Remaining : 16.65
Demand : 5.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.20
Construction Started
Physical Progress:
At start of FY 2024-2025 : 76 %
Up to Date : 76 %
Sanction on :
7 years 6 months ago
04 Jan 2017
Tentative Completion date:
8 months 1 week from now
30 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 15: AIP Nodal
Bottelneck: no issue
इस कार्यालय के पत्रांक 521/14सी0 दि0 01.04.2021 एवं 863/14सी0 दि0 05.07.2021 के द्वारा प्रभागीय लौगिग प्रबन्धक उत्तराखण्ड़ वन विभाग निगम पौडी को बाधक वृक्षो के कटान हेतु पत्र लिखा गया है। इस कार्यालय के पत्रांक 741/14 सी0 दि0 30.04.2024 द्वारा अपर प्रमुख वन संरक्षक एवं नोडल अधिकारी, वन संरक्षण भूमि संरक्षण, भूमि सर्वेक्षण निदेशालय इन्दिरा नगर, फारेस्ट काॅलोनी देहरानदून को विधिवत स्वीकृति जारी करने के सम्बन्ध में पत्र लिखा गया है। द्वितीय चरण स्टेज-1 की स्वीकृति प्राप्त । पहाड कटान का कार्य प्रगति पर। -- as on 03-Jun-2024
Physical Peramenters