Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 5 | 0 |
72W329 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 5937/।।।(2/18-39 (एम0एल0ए0)/2017 टी0सी0 दि0 07.12.2018
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 31.75 Lacs
Resanction Cost : 31.75 Lacs
Exp. Upto Last Fy : 1.79 Lacs
For CFY 2024-2025
Remaining : 29.96 Lacs
Demand : 2.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 1.79 Lacs
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 15 %
Up to Date : 15 %
Sanction on :
5 years 5 months ago
07 Dec 2018
Tentative Completion date:
1 year 10 months from now
30 Mar 2026
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 04: DFO
Bottelneck: no issue
FP/UK/ROAD/452852/2023 Dt 28-11-2023 के द्वारा आॅनलाईन अपलोड कर दी गयी है। आज के स्टेटस के अनुसार प्रभागीय वनाधिकारी स्तर पर लम्बित है। समरेखण में बांज के वृक्षों की संख्या अधिक होने के कारण बांज के वृक्षों की संख्या कम करने हेतु समरेखण परिवर्तन का सुझाव दिया गया है। जिस हेतु ग्रामवासियों की सहमति के अनुसार समरेखण परिवर्तन की कार्यवाही गतिमान है। -- as on 03-Apr-2024
Physical Peramenters