Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 3 | 0 |
72W371 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 2177/।।।(2)/20-38 (एम0एल0ए0)/2017 दि0 04.12.2020
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
18.84
Resanction Cost :
18.84
Tentative Cost :
0.00
Saving
18.84
Exp. Upto Last Fy : 0.80
For CFY 2024-2025
Remaining : 18.04
Demand : 2.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.80
Survey work done
Physical Progress:
At start of FY 2024-2025 : 10 %
Up to Date : 10 %
Sanction on :
3 years 7 months ago
04 Dec 2020
Tentative Completion date:
8 months 1 week from now
30 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
सर्वेक्षण का कार्य पूर्ण। समरेखण आपत्तियो में प्राप्त। आपत्तियो का निराकरण समरेखण पुनः पत्रांक 1495/18सी0 दि0 21.11.2022 द्वारा वृत्तीय कार्यालय को अनुमोदन हतु प्रेषित। ग्रामीणों द्वारा समरेखण में विवाद। -- as on 30-Dec-2023
Physical Peramenters