Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 2 | 0 |
72W401 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0 सं0- 2383/।।।(2)/21-39 (एम0एल0ए0)2017 टी0सी0-3 दि0 04.08.2021
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 0.80 Lacs
Resanction Cost : 0.80 Lacs
Exp. Upto Last Fy : 0.69 Lacs
For CFY 2024-2025
Remaining : 0.11 Lacs
Demand : 0.11 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.69 Lacs
Survey work done
Physical Progress:
At start of FY 2024-2025 : 60 %
Up to Date : 60 %
Sanction on :
2 years 9 months ago
04 Aug 2021
Tentative Completion date:
10 months 1 week from now
30 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
मुख्य अभियन्ता, लो0नि0वि0 पौडी के पत्रांक 4586/12(28) याता0(बैजरो)- पौड़ी /2023 दि0 21.07.2023 द्वारा सचिव, लो0नि0वि0, उत्तराखण्ड शासन, देहरादून को प्रेषित। द्वितीय चरण की स्वीकृति प्राप्त। -- as on 03-Apr-2024
Physical Peramenters